Concrete Calculator

Add your slab, footings, post holes or steps. You get cubic yards, how many bags of each size, whether to order a truck, and the gravel, rebar and control joints that go with a slab.

Your pour

1. What you're pouring
Length
ft
in
Width
ft
in

1.48 yd³ before extra

2. Under and inside the slab
3. Extra & prices (optional)

Concrete

1.63 yd³

incl. 10% extra

80 lb bags

74

or 98 x 60 lb

Ready-mix order

1.75 yd³

rounded to ¼ yd

Cost

—

add prices

Bags or a truck: 74 bags is a long day of mixing. A 1.75 yd³ load usually comes with a short-load fee — price both.

Preview

Thickness drawn larger so you can see it. Gravel base below, rebar shown through the surface, control joints as grooves.

Bags per size

74

80 lb bags · 0.6 ft³ each

98

60 lb bags · 0.45 ft³ each

147

40 lb bags · 0.3 ft³ each

Shopping list

  • ✓Concrete: 1.63 yd³ incl. 10% extra (44.0 cu ft)
  • ✓Bagged mix: 74 x 80 lb or 98 x 60 lb or 147 x 40 lb
  • ✓Ready-mix order: 1.75 yd³
  • ✓Gravel base (4" compacted): 1.63 yd³ ≈ 2.3 tons
  • ✓#3 or #4 rebar on 18" grid: 9 x 20 ft sticks (157 ft) + chairs and tie wire
  • ✓Control joints every 10 ft: 10 ft (groover or saw)
  • ✓Form boards & stakes, screed board, float, edger, gloves and eye protection

Bag yields from the QUIKRETE Concrete Mix data sheet. Structural footings and slabs may need a permit and an engineer — check local code.

How much concrete do I need?

Multiply length x width x thickness in feet to get cubic feet, then divide by 27 for cubic yards. Thickness is the step people get wrong: 4 inches is 0.33 ft, not 0.4. Add about 10% for uneven ground, form bowing and spills.

Example: a 12' x 12' patio at 4" is 12 x 12 x 0.333 = 48 cu ft, or 1.78 yd³. With 10% extra that's 1.96 yd³ — about 88 bags of 80 lb mix, or a 2-yard ready-mix order.

How many bags make a yard?

BagYield per bagBags per cubic yard
80 lbabout 0.60 cu ft45
60 lbabout 0.45 cu ft60
40 lbabout 0.30 cu ft90

These are the yields printed on standard concrete mix bags. High-strength and fast-setting mixes are close but check the bag.

Bags or a ready-mix truck?

Under about a cubic yard, bags are simplest. Between one and three yards it depends on your price and patience — that's 45 to 135 bags to mix by hand, while a small truck load often carries a short-load fee. Above three yards, order ready-mix: you can't mix and place that many bags before the first ones start to set. The calculator rounds a truck order up to the nearest quarter yard.

How thick should a slab be?

Walks and patios are usually 4 inches. Driveways for cars are 4 to 5 inches, and 6 inches for pickups, RVs or heavy use. Slabs go on a compacted gravel base — typically 4 inches — which drains water and spreads the load.

Rebar, mesh and control joints

A grid of rebar (often #3 or #4 at 12 to 24 inches) or welded wire mesh helps hold a cracked slab together; it doesn't stop cracks. Control joints decide where cracks happen. A common rule is joint spacing in feet of about 2.5 times the slab thickness in inches, so every 10 feet for a 4" slab. Cut them a quarter of the slab's depth.

Post holes and footings

For a fence post, dig a hole about three times the post's width and about a third of its length deep, and subtract the post itself from the volume — the calculator does both. Deck and structural footings must go below your local frost line and may need a permit.

Building a patio? Pair this with the tile calculator or plan the room next to it with the flooring and paint calculators.